Contract amendment
A contract amendment is to a formal change or modification to the terms and conditions of an existing construction contract. This can be necessary to accommodate adjustments that may arise during the course of a project, for example:
- Changes in the scope of work to be performed, including additions, deletions, or modifications to the original project plans and specifications.
- Adjustments to the project timeline, which might include extending or shortening the completion date or adjusting intermediate milestones.
- Modifications to the contract price, which could involve increasing or decreasing the overall budget based on the changes to the scope of work or other factors. It can also include changes to the payment schedule.
- Substitutions or changes in materials, products, or workmanship specifications that were initially agreed upon.
- Adjustments to ensure the contract remains compliant with any new or updated laws, regulations, or standards that may come into effect during the project.
- Revisions to the allocation of risks and responsibilities between the parties involved, such as changes in insurance requirements or liability clauses.
- Changes to the methods and processes for resolving disputes, which could involve amending arbitration clauses, mediation procedures, or other conflict resolution mechanisms.
Contract amendments are typically documented through formal written agreements signed by all parties involved in the original contract. This documentation ensures that there is a clear, mutual understanding of the changes and helps prevent disputes related to misunderstandings or misinterpretations of the modifications.
See also: Variations.
[edit] Related articles on Designing Buildings
- Abortive work in building design and construction.
- Architect's instruction.
- Change control procedure for building design and construction.
- Change order for construction contracts.
- Compensation event.
- Confirmation of verbal instruction.
- Contract sum.
- Extension of time EOT in construction contracts.
- How to prepare a claim for an extension of time.
- Loss and expense.
- Payment for extra work.
- Prime cost sum.
- Provisional sum.
- Relevant event.
- Relevant matter.
- Scope of work.
- Valuation of interim payments.
- Variations.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.